Week of December 9, 2019
Annual Water Main Replacement Project
For the week of December 9, the contractor will continue installing new water main on 7th Court between Broadway and Santa Monica Blvd. The contractor will begin digging to identify existing utilities and verifying the alignment of the new water main on Airport Ave between 23rd Street and Bundy Dr. On Thursday December 12, 2019 between 8 am and 4 pm on Cedar St between Lincoln Blvd and 11th Street the contractor will be shutting off the water to connect the newly installed water main on Cedar St at Lincoln Blvd. Traffic will be closed to through traffic on 7th Court, Cedar St. and reduce traffic to one lane on Airport Ave. Please use alternate routes whenever possible.
Advanced Traffic Management System, Phase 5 Project
For the week of December 9, this project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Avenue and 26th Street. The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network.
Fire Station #1 Construction Project
For the week of December 9, construction will continue throughout the project area located at 1377 7th Street which will affect the sidewalk and parking lane on the east side of 7th Street just north of Santa Monica Boulevard. Sidewalk and parking lane will continue to be closed all day/night through the month. If you have any questions or concerns, please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675.
Downtown /Expo Vehicle Barriers Project
For the week of December 2, there will be no planned closures on Colorado Ave between 4th St and 5th St. Work to install bollards will resume and be completed at a later time. Please contact Saad Malim at (310) 458-8293 with any questions/concerns regarding this project.
Annual Wastewater Main Project
For the week of December 9, sewer main repair work will take place on California Pl North between 23rd Ct and Chelsea Avenue, . Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
City Yards Modernization Project
For the week of December 9, construction will impact the project area located at 2500 Michigan Avenue, which will affect the sidewalk and parking lane on the north side of Delaware Avenue just east of 24th Street. Please contact Project Manager Sebastian Felbeck at (310) 434-2675with any questions/concerns regarding this project.
Storm Drain & Drainage Improvements Project
For the week of December 9, drainage and pavement improvements will take place at the intersection of 2nd St and Arizona Ave. during nighttime hours (10PM-6AM). Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
Annual Paving, Snap Parking, & Beach Parking Project
For the week of December 2, manhole and valve covers will be raised to grade on 17th Street from California Avenue to Wilshire Boulevard and on 7th Street from Palisades Avenue to Wilshire Boulevard. Please contact Jason Hoang at (310) 458-8721 with any questions/concerns regarding this project.