ANNUAL WATER MAIN REPLACEMENT PROJECT
For the week of March 2, the contractor will begin restoring the striping of the trench area of the newly installed water main on 7th Court between Santa Monica Boulevard and Broadway, Pico Boulevard between Main Street and 4th Street and on Pier Avenue be-tween Main Street and 2nd Street. The contractor will be connecting the new water main on Airport Avenue east of 23rd Street.; Traffic will be reduce to one lane in each direction on Pico Blvd between Main St and 4th St, Broadway @ 7th Ct, Santa Monica Blvd @ 7th Ct and to one lane on Airport Ave. Please use alternate routes whenever possible. Please contact Carlos Rosales at (310) 458-8721 with any questions/concerns regarding this project.
ADVANCED TRAFFIC MANAGEMENT SYSTEM, PHASE 5 PROJECT
For the week of March 2, this project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Ave and 26th St.; The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network. We appreciate your patience during the project, to provide this safety improvement and public enhancements. If you have any questions or concerns, please contact Andrew Maximous at (310) 458-8291.
FIRE STATION #1 CONSTRUCTION PROJECT
For the week of March 2, construction will continue throughout the project area located at 1377 7th Street which will affect the sidewalk and parking lane on the east side of 7th Street just north of Santa Monica Boulevard. Sidewalk and parking lane will continue to be closed all day/night through the month. If you have any questions or concerns, please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675.
ANNUAL WASTEWATER MAIN PROJECT
For the week of March 2, sewer main repair work will be taking place in the Lincoln Ct Alley between Maple Pl North & Maple St and on Maple St between Lincoln Ct and Lincoln Blvd. Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
CITY YARDS MODERNIZATION PROJECT
For the week of March 2nd, construction will impact the project area located at 2500 Michigan Ave, which will affect the sidewalk and parking lane on the north side of Delaware Ave just east of 24th St. Please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675 with any questions/concerns regarding this project.
STORM DRAIN & DRAINAGE IMPROVEMENTS PROJECT
For the week of March 2, drainage improvements to install a catch basins will take place at 25th St and Montana Ave. Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
ANNUAL PAVING, SNAP PARKING, & BEACH PARKING PROJECT
For the week of March 2, work will take place in the 2800 Donald Douglas Loop North parking lot where we will be reconstructing the asphalt pavement. Please contact Jason Hoang at (310) 458-8721 with any questions/concerns regarding this project.