Week of April 20, 2020
Annual Water Main Replacement Project
For the week of April 20, the contractor will be working on Airport Avenue between 23rd Street and Bundy Drive installing new services and water meters. One lane of traffic in each direction will be maintained at all times on Pico Blvd. and on Airport Avenue flaggers will be used to direct traffic. Please use alternate routes whenever possible. If you have any questions or concerns, please contact Carlos Rosales at (310) 458-8721, x2620.
Advanced Traffic Management System, Phase 5 Project
For the week of April 20, this project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Ave and 26th St.; The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network. We appreciate your patience during the project, to provide this safety improvement and public enhancements. If you have any questions or concerns, please contact Jay Dinkins at (310) 458-8291.
Fire Station #1 Construction Project
For the week of April 20, construction will continue throughout the project area located at 1377 7th Street which will affect the sidewalk and parking lane on the east side of 7th Street just north of Santa Monica Boulevard. Sidewalk and parking lane will continue to be closed all day/night through the month. If you have any questions or concerns, please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675.
Annual Wastewater Main Project
For the week of April 20, sewer main repair work will be taking place in the Lincoln Ct Alley between Olympic Blvd and Colorado Ave. Sewer main repair work will also be taking place along Centinela Ave between Ocean Park Blvd and Pearl St. Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
City Yards Modernization Project
For the week of April 20, construction will impact the project area located at 2500 Michigan Ave, which will affect the sidewalk and parking lane on the north side of Delaware Ave just east of 24th St. Please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675 with any questions/concerns regarding this project.
Storm Drain & Drainage Improvements Project
For the week of April 20, there is no planned work for this project. Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
Annual Paving, Snap Parking, & Beach Parking Project
For the week of April 20, roadway striping will take place on Broadway from 16th St to 21st St and on Pico from Cloverfield to 26th St., weather permitting. Please contact Jason Hoang at (310) 458-2201 x5385 with any questions/concerns regarding this project.