EXPO LIGHT RAIL LINE:
Expo Light Rail Line extension from Culver City to Santa Monica is scheduled to open on May 20, 2016.
COLORADO ESPLANADE:
Construction work on Colorado Ave. will continue daytime Monday through Friday. Pedestrian access is accommodated by use of temporary barricaded pathways marked with signage. Please use caution when navigating through the work zones on Colorado Ave. at 4th St., Main St., 2nd St., and Ocean Ave. Expect minor delays at the intersection of Colorado and Ocean Ave. For more information contact Gene Higginbotham, Project Manager, at (310) 458-8729.
CALIFORNIA INCLINE BRIDGE REPLACEMENT PROJECT:
The California Incline will be closed until Summer 2016 while construction crews demolish the existing structure and build the new bridge and roadway. Motorists are advised to use Ocean Avenue (via Moomat Ahiko Way) and Lincoln Boulevard as alternate routes. For more information on this project, please contact: (888-303-6026 or incline@smgov.net).
WASTEWATER MAIN REPLACEMENT PROJECT:
The contractor will continue with restoration work of the concrete walkway on Ocean Front Walk at Moss Avenue. Should you have any questions, please contact Carlos Rosales, Project Manager (310) 458-8721 ext. 2620.
SAN VICENTE PUMP STATION EMERGENCY GENERATOR
The contractor will continue with testing of the new engine driven standby generator. No street improvement work is scheduled. Should you have any questions, please contact Carlos Rosales, Project Manager (310) 458-8721 ext. 2620.
BUFFER PARK CONSTRUCTION PROJECT:
As part of the construction of the new Buffer Park at 2909 Exposition Blvd, the sidewalk on the eastside of Stewart St. at Exposition Blvd. and along Exposition Blvd to Dorchester Ave. will be closed. Construction will also close part of the northbound bike lane on Stewart Street at the intersection of Stewart St. and Exposition Blvd. Directional signage has been posted alerting pedestrians and bicyclists of the impediments caused by the construction project. This closure will allow for the construction of a new sidewalk on a portion of Stewart St. and Exposition Blvd as well as park pathways and landscaping adjacent to the affected areas. For more information contact Sebastian Felbeck, Construction Manager, at (310) 434-2675.
CROSSWALK RENEWAL PROGRAM:
Contractor crews will begin nighttime crosswalk removal and restriping at the intersections of Wilshire/2nd, 18th and 19th Street. Please be advised that striping removal will generate noise and dust. Temporary traffic control signs will be deployed to guide vehicular traffic in and around work areas. Please contact Kori Jones, Street & Fleet Services, (310) 458-2201 ext. 5002 or kori.jones@smgov.net with any questions/concerns regarding this project.
ANNUAL PAVING PROJECT:
The contractor will continue repairing decorative sidewalk in the downtown area along 2nd and 3rd streets between Colorado Ave and Wilshire Blvd. Impact to traffic shall be minimal. One lane will remain open in each direction but please obey all construction-related signs including “No Parking” signs. For more information contact Hany Demitri, Civil Engineer at (310) 458-8721 ext. 5385.