• About Us
  • Our People
  • Contact Us
  • Advertise
    • ADVERTISING WITH SMDP
    • Digital Advertising
    • Legal Notices
    • Marriage & Other Special Announcements
    • Obituary
  • Back Issues
  • Social
    • Instagram
    • Facebook
    • LinkedIn
    • YouTube
    • X
Tuesday, May 20, 2025
No Result
View All Result
Santa Monica Daily Press
SUPPORT US
  • News
    • Crime
    • Education
    • Environment
    • Homelessness
    • Transportation
  • Community
    • ‘Tis The Season
    • Most Loved
    • Non Profit
    • Pet of the week
    • Obituaries
  • Business
    • Development
    • Real Estate & Housing
  • Lifestyle
    • Food
    • Entertainment
    • Health
    • Travel
  • Opinion
    • Editorial
    • Columns
    • Letters
  • Sports
  • Events
  • Advertise
    • Print Advertising
    • Digital Advertising
    • Legal Notices
    • Marriage & Other Special Announcements
    • Obituary Form
  • Back Issues
Santa Monica Daily Press
  • News
    • Crime
    • Education
    • Environment
    • Homelessness
    • Transportation
  • Community
    • ‘Tis The Season
    • Most Loved
    • Non Profit
    • Pet of the week
    • Obituaries
  • Business
    • Development
    • Real Estate & Housing
  • Lifestyle
    • Food
    • Entertainment
    • Health
    • Travel
  • Opinion
    • Editorial
    • Columns
    • Letters
  • Sports
  • Events
  • Advertise
    • Print Advertising
    • Digital Advertising
    • Legal Notices
    • Marriage & Other Special Announcements
    • Obituary Form
  • Back Issues
No Result
View All Result
Santa Monica Daily Press
No Result
View All Result
Home News

Expo light rail facing construction delays

by David Mark Simpson
May 14, 2015
in News, Transportation
Rail construction complete at Lincoln and Colorado

Works install tracks at the intersection of Colorado Avenue and Lincoln Boulevard last week. (Paul Alvarez Jr.)

0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

You might have noticed trains testing along the second phase of the Expo Light Rail (though not in Santa Monica), but the construction process has fallen behind schedule.

Despite the delays, Expo officials are "cautiously optimistic" that the trains will be moving passengers by March of April of next year.

"Right now, as far as substantial completion goes, the contractor's probably three to four months behind schedule but as far as construction goes," Expo's Chief Project Officer Eric Olson told the Daily Press. "We're still looking at construction being done in the September, early October timeframe, which would then allow Metro to go into their pre-revenue operations and testing, which we still think supports a March or April revenue service date, which is pretty much what we've all been looking at over the last year or year and half of the project."

The contractor, Skanska Rados, has had issues getting track work installed, Olson said. Additionally, a "very special vibration dampening piece of equipment" had to be installed.

"We had some settlement on a retaining wall at Centinela Avenue so we had to hold off doing some things there," Olson said. "That kind of slowed the track work up a little bit also."

When asked who's responsible for the delays, Olson said it depends who you ask.

"I mean, there's a little bit on both sides associated with us falling behind a little bit," he said.

The Daily Press reached out to several Skanska Rados officials about delays.

Jay Weisberger, their West Coast spokersperson responded: "We are also optimistic that we will be able to complete the project for revenue service next spring. We are working closely with the Expo Authority and our subcontractors to ensure completion in that time frame."

At the end of the day, Olson said, an early construction completion would not necessarily have impacted the opening of the second phase of the project.

"It's highly unlikely because Metro is also in a vehicle procurement and we need the vehicles to open up the line," he said. "If you look at the last Expo Board meeting, Metro did a presentation on the vehicle delivery and they're looking at the vehicles starting to come in at the end of June, early July. Realistically they couldn't have gone into pre-revenue until sometime in September, October to begin with, so that's why we've always been forecasting a revenue operation date in March or April."

Trains started testing in Los Angeles last month but they're still a few months away from Santa Monica, Olson said.

"It's probably going to be in July," he said. "You might see a car out there in mid to late June. Come July you'll start seeing the trains running pretty regularly up and down Colorado Avenue and the rest of the guideway in Santa Monica."

They're running tests in Santa Monica, he said, but not yet of trains.

"It's coming, it's coming," Olson said. "We're pushing. The contractor's pushing to make sure we hit these dates so we just need to stay on top of that and make sure when we're testing, hopefully we don't have any problems with the testing, any issues there. So far, so good, so we're cautiously optimistic that we're going to stay on schedule."

dave@www.smdp.com

Tags: colorado avenueconstructiondelaysExpo Light Railgetting aroundMetroNewspublic transitSanta Monicasanta monica newsskanska radostrainstransportation

David Mark Simpson

Recent News

Outlandish taps Brazil market as Santa Monica retail lab goes global

May 20, 2025

St. Monica Preparatory High School Boys Golf Team Dominates In Record Breaking Season

May 20, 2025
Santa Monica Education Foundation Announces $25,000 Matching Gift from Fairmont Miramar Hotel

Man shot during altercation outside Fairmont Miramar Hotel

May 19, 2025
Attempted robbery ends in fatal shooting on Third Street Promenade

Attempted robbery ends in fatal shooting on Third Street Promenade

May 19, 2025
Faced with budget woes, Gavin Newsom wants more tax credits for Hollywood

Faced with budget woes, Gavin Newsom wants more tax credits for Hollywood

May 19, 2025
Midnight hit and run on the PCH sends pedestrian to hospital

Caltrans presents long-term vision for safer, multimodal PCH through Malibu

May 19, 2025
TikTok ban won’t happen in California this year

Easily distracted? How to improve your attention span

May 17, 2025
Santa Monica cyclist recalls attack on Third Street Promenade in broad daylight

Santa Monica cyclist recalls attack on Third Street Promenade in broad daylight

May 17, 2025
Santa Monica Daily Press

Copyright © 2025 SMDP. All Rights Reserved.

Navigate Site

  • About
  • Our People
  • Print Advertising
  • Digital Advertising
  • Legal Notices
  • Obituary
  • SMDP Finder
  • Privacy Policy
  • Back Issues

Follow Us

No Result
View All Result
  • News
  • Community
  • Business
  • Lifestyle
  • Opinion
  • Sports
  • Events
  • ‘Tis The Season
  • Advertise
    • Print Advertising
    • Digital Advertising
    • Legal Notices
    • Obituary
    • Marriage & Other Special Announcements
  • Back Issues
  • Contact Us
  • Support Us

Copyright © 2025 SMDP. All Rights Reserved.

Skip to content
Open toolbar Accessibility Tools

Accessibility Tools

  • Increase TextIncrease Text
  • Decrease TextDecrease Text
  • GrayscaleGrayscale
  • High ContrastHigh Contrast
  • Negative ContrastNegative Contrast
  • Light BackgroundLight Background
  • Links UnderlineLinks Underline
  • Readable FontReadable Font
  • Reset Reset