Attached is KBUG information for the week of July 2, 2018:
Street Lighting Modernization Program
For the week of July 2, construction will take place throughout the project area bounded by Pico Blvd to the north, Ocean Park Blvd to the south, Lincoln Blvd to the west, and 16th St to the east. Parking on streets within the project area may temporarily be impacted. Please contact Robert Zak, Project Manager at (310) 458-2283 with any questions/concerns regarding this project.
Parking Structure #5 Tenant Improvement Project
For the week of July 2, construction will take place in Parking Structure #5 at 1440 4th street and anticipated to affect the sidewalk in front of the building with the sidewalk pedestrian tunnel, lasting until 7/31/18. During this time, there will be intermittent closure of a single lane of south-bound traffic between 8 a.m. and 3 p.m. Monday thru Friday. Should you have any questions, please contact Tim Purcell, Project Manager (310) 458-2205 ext. 5027
Parking Structure Repair Project
For the week of July 2, Parking Structures #2, #4, and #5 will be undergoing maintenance and repair work. Construction may temporarily impact parking. Entrances and exits will remain open for smooth traffic flow. Please contact Robert Zak, Project Manager at (310) 458-2283 with any questions/concerns regarding this project.
Edison Language Academy Project
For the week of July 2, construction crews will be cautioning off sidewalks at various crosswalk locations near Edison Language Academy. Effected Crosswalks include: Delaware Avenue & 22nd Street; Kansas Avenue & 27th Street; Stewart Street & Kansas Avenue. Crews will be closing half the sidewalk for demolition and reconstruction of concrete curbs and ramps. Intermittent lane closures will occur. Parking on streets near the crosswalks will be temporarily impacted. Please contact Gene Higginbotham, Construction Manager at (310) 458-8729 with any questions/concerns regarding this project.
EPA Grant Funded Water Infrastructure Reliability Improvement Project
For the week of July 2, construction work will take place consisting of surveying and potholing (minor road excavations) in the following locations: 17th from Pearl to Ocean Park, Ocean Park from 14th to 18th, Ocean Ave from Pico to Bay, Ashland from 3rd to 4th, and Grant from 6th to Lincoln. Work will take place in the roadway, but will not create any lane closures. Please contact Carlos Rosales, Construction Manager at (310) 458-8721, x2620 with any questions/concerns regarding this project.