Street Lighting Modernization Program
No work planned for the week of November 12. Please contact Robert Zak, Project Manager at (310) 458-2283 with any questions/concerns regarding this project.
Parking Structure #5 Tenant Improvement Project
For the week of November 12, construction will take place in Parking Structure #5 at 1440 4th street and anticipates affecting the sidewalk in front of the building with the sidewalk pedestrian tunnel, lasting until 11/30/18 During this time, there may be intermittent closures of a single lane of south-bound traffic between 8:00 am and 3:00 pm Monday thru Friday. Should you have any questions, please contact Tim Purcell, Project Manager (310) 458-2205 ext. 5027
Parking Structure Repair Project
No work planned for the week of November 12. Please contact Robert Zak, Project Manager at (310) 458-2283 with any questions/concerns regarding this project.
EPA Grant Funded Water Infrastructure Reliability Improvement Project
For the week of November 12, the contractor will be connecting the newly installed water main on Ocean Park Boulevard at 14th Street and 16th Street. The contractor will also continue installation of new water main on Grant Street between 6th Street and Lincoln Blvd. Traffic will be reduced to one lane on Ocean Park Blvd. and closed to thru traffic on Grant Street. Please use alternate routes whenever possible.
LA Metro public art project – “Tears Of Santa Monica”
For the week of November 12, construction will take place at the westerly wall of the Expo light rail station at 4th and Colorado. The project will run from Summer until the early part of Fall. Intermittent easterly sidewalk and northbound 4th Street lane closures will take place. For any questions or further information, please contact Henry Servín, at (310) 458-8291 or Leticia Ivins at LA Metro at IvinsL@metro.net with any questions/concerns regarding this project.
Bike Network Linkages Project
For the week of November 12, work is scheduled to take place throughout various locations within the city. The project consists of applying new green paint to bicycle lanes, bike rack installation, and intersection work that requires lane closures. Please contact Jason Hoang, Project Manager at (310) 458-8721, x5385 with any questions/concerns regarding this project.