Week of March 30, 2020
Annual Water Main Replacement Project
For the week of March 30, the contractor will begin digging to identify existing utilities and verifying the new water main alignment on Pico Blvd between Lincoln Blvd and 12th Court. The contractor will also be working on Airport Avenue btwn 23rd Street and Bundy Drive on Wednesday March 28, 2020 between the hours of 8:00 pm to 2:00 am. One lane of traffic in each direction will be maintained at all times on Pico Blvd. and on Airport Avenue flaggers will be used to direct traffic. Please use alternate routes whenever possible. Please contact Carlos Rosales at (310) 458-8721 with any questions/concerns regarding this project.
Advanced Traffic Management System, Phase 5 Project
For the week of March 30, this project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Ave and 26th St.; The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network. We appreciate your patience during the project, to provide this safety improvement and public enhancements. If you have any questions or concerns, please contact Andrew Maximous at (310) 458-8291.
Fire Station #1 Construction Project
For the week of March 30, construction will continue throughout the project area located at 1377 7th Street which will affect the sidewalk and parking lane on the east side of 7th Street just north of Santa Monica Boulevard. Sidewalk and parking lane will continue to be closed all day/night through the month. If you have any questions or concerns, please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675.
Annual Wastewater Main Project
For the week of March 30, sewer main repair work will be taking place in the Lincoln Ct Alley between Olympic Blvd and Colorado Ave. Sewer main repair work will also be taking place in the along Centinela Ave between Ocean Park Blvd and Pearl St. Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
City Yards Modernization Project
For the week of March 30, construction will impact the project area located at 2500 Michigan Ave, which will affect the sidewalk and parking lane on the north side of Delaware Ave just east of 24th St. Please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675 with any questions/concerns regarding this project.
Storm Drain & Drainage Improvements Project
For the week of March 30, there is no planned work for this project. Please contact Saad Malim at (310) 458-8721 with any questions/concerns regarding this project.
Annual Paving, Snap Parking, & Beach Parking Project
For the week of March 30, roadway striping will take place on Broadway from 16th St to 21st St, weather permitting. Please contact Jason Hoang at (310) 458-8721 with any questions/concerns regarding this project.
Palisades Park Brick Stairwell Replacement Project
For the week of March 30 thru April 3rd, access will be closed to the pedestrian bridge leading from Palisades Park (near Camera Obscura) to Beach Parking Lot 1 North. This project will address necessary repairs to existing brick walkway leading to bridge entrance. For questions about this project please email Streets.Mailbox@smgov.net or call (310) 458-499.