LA METRO PUBLIC ART PROJECT – “TEARS OF SANTA MONICA”
For the week of June 24, artwork installation is slated to resume and run from Summer until the late part of Fall at the westerly wall of the Expo light rail station at 4th St and Colorado Ave. Intermittent easterly sidewalk and northbound 4th St lane closures will take place. Please contact Henry Servin at (310) 458-8291 or Letitia F. Ivins at LA Metro at IvinsL@metro.net and (213) 922-2721 with any questions/concerns regarding this project.
For the week of June 24, work is scheduled to take place on 31st St. The project consists of applying new green paint to existing bicycle lanes. Please contact Jason Hoang, Project Manager at (310) 458-8721 with any questions/concerns regarding this project.
ANNUAL WATER MAIN REPLACEMENT PROJECT
For the week of June 24, the contractor will begin saw cutting and potholing on Pico Boulevard between Main Street and 4th Street. Traffic will be reduced to one lane in each direction on Pico Blvd. The new water main connection continues during the week and the water service shutdown on June 25th on Raymond Avenue between 7th Street and Lincoln Blvd. Traffic will be closed to through traffic. Please contact Carlos Rosales, Project Manager at (310) 458-2620 with any questions/concerns regarding this project.
ADVANCED TRAFFIC MANAGEMENT SYSTEM, PHASE 5 PROJECT
For the week of June 24, construction will continue on the Advanced Traffic Management System, Phase 5 Project. This project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Ave and 26th St. The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network. We appreciate your patience during the project, to provide this safety improvement and public enhancements. Please contact Andrew Maximous, Project Manager at (310) 458-8291 with any questions/concerns regarding this project.
FIRE STATION #1 CONSTRUCTION PROJECT
For the week of June 24, construction will continue throughout the project area located at 1377 7th Street which will affect the sidewalk and parking lane on the east side of 7th Street just north of Santa Monica Blvd. Sidewalk and parking lane will continue to be closed all day/night through the month. Please contact Senior Construction Manager Sebastian Felbeck at (310) 434-2675 with any questions/concerns regarding this project.
For the week of June 24, alley renewal will take place at various locations throughout the city. No traffic impacts on surface streets, however temporary closures of alleys may occur. Residential parking passes will be issued, as necessary. Please contact Robin Jarrett at (310) 863-6773 with any questions/concerns regarding this project.
DOWNTOWN /EXPO VEHICLE BARRIERS PROJECT
For the week of June 24, the westbound lane on Colorado Avenue will be closed between 4th and 5th Street from 8am until 5pm while we work on retractable bollard installations. There will be daily closures of Colorado Avenue for the duration of the project, which is scheduled to be completed on July 26, 2109. Please contact Brian Ochoa at (310) 486-9632 with any questions/concerns regarding this project.
ANNUAL WASTEWATER MAIN PROJECT
For the week of June 24, sewer main repair work will take place on Pine Street between 11th Street and Euclid Street.
Please contact Gene Higginbotham at (310) 458-8729 with any questions/concerns regarding this project.