• About Us
  • Our People
  • Contact Us
  • Advertise
    • ADVERTISING WITH SMDP
    • Digital Advertising
    • Legal Notices
    • Marriage & Other Special Announcements
    • Obituary
  • Back Issues
  • Social
    • Instagram
    • Facebook
    • LinkedIn
    • YouTube
    • X
Friday, May 16, 2025
No Result
View All Result
Santa Monica Daily Press
SUPPORT US
  • News
    • Crime
    • Education
    • Environment
    • Homelessness
    • Transportation
  • Community
    • ‘Tis The Season
    • Most Loved
    • Non Profit
    • Pet of the week
    • Obituaries
  • Business
    • Development
    • Real Estate & Housing
  • Lifestyle
    • Food
    • Entertainment
    • Health
    • Travel
  • Opinion
    • Editorial
    • Columns
    • Letters
  • Sports
  • Events
  • Advertise
    • Print Advertising
    • Digital Advertising
    • Legal Notices
    • Marriage & Other Special Announcements
    • Obituary Form
  • Back Issues
Santa Monica Daily Press
  • News
    • Crime
    • Education
    • Environment
    • Homelessness
    • Transportation
  • Community
    • ‘Tis The Season
    • Most Loved
    • Non Profit
    • Pet of the week
    • Obituaries
  • Business
    • Development
    • Real Estate & Housing
  • Lifestyle
    • Food
    • Entertainment
    • Health
    • Travel
  • Opinion
    • Editorial
    • Columns
    • Letters
  • Sports
  • Events
  • Advertise
    • Print Advertising
    • Digital Advertising
    • Legal Notices
    • Marriage & Other Special Announcements
    • Obituary Form
  • Back Issues
No Result
View All Result
Santa Monica Daily Press
No Result
View All Result
Home Business

City of Santa Monica projects nearing completion

by Madeleine Pauker
April 24, 2020
in Business, Covid-19, Development, Featured, Health, Lifestyle, News, Real Estate & Housing
City of Santa Monica projects nearing completion

Photo by Ross Furukawa

0
SHARES
0
VIEWS
Share on FacebookShare on Twitter

Although the city of Santa Monica is delaying, scaling back or canceling $40.4 million in capital projects through next June as municipal revenues dry up during the coronavirus shutdown, several major projects that predate the crisis are finished or nearing completion.

The city will cut its budget for capital improvement projects by 75%, eliminating or suspending projects that were in the bidding process, said city spokesperson Constance Farrell. Projects that will continue are either funded through grants or self-sustaining funds separate from the city’s general fund, which is projected to see a shortfall of $72 million this fiscal year and an additional gap of $154 million next fiscal year due to a steep drop in sales, hotel and parking tax revenues.

Some projects were slated to open soon, but ribbon-cutting ceremonies have been postponed indefinitely due to stay-at-home orders.

City Hall East, also known as the City Services Building, has been under construction since fall 2017 and was supposed to open on Earth Day. The $76.8 million addition to City Hall is complete, Farrell said.

When the three-story, 50,000-square-foot building opens, it will house 240 city employees in departments such as planning, traffic management and cultural affairs who currently work in leased offices elsewhere in downtown Santa Monica. The city’s permit counter will also move from City Hall to the ground floor of the new building.

At $1,529 per square foot, City Hall East is substantially more expensive per square foot than comparable municipal projects.

The city of Long Beach completed its new civic center last year, which cost $553 million in total and $884 per square foot.

Orange County is building a new county headquarters in Santa Ana, which is projected to cost $198 million or $779 per square foot. The budget for the project also includes another $195 million to pay off bonds issued to fund construction.

Santa Monica’s City Hall East, which will be financed by 30-year lease revenue bonds, is projected to pay for itself by 2047.

City Hall East will eliminate the need to lease office space for city employees, which was expected to increase from $2.5 million to $30 million annually over the next 30 years, according to a 2017 report.

Lauded as the most sustainable municipal building in the United States, City Hall East will produce its own energy and water, saving hundreds of millions of dollars in utilities costs over its 100-year lifespan.

As part of the City Hall East project, City Council in January authorized $8 million in improvements to City Hall. The 1939 building was set to receive upgraded heating, ventilation and air-conditioning systems, a new roof, and new staff workstations and meeting space.

But because of the budget crisis, the city will only upgrade City Hall to meet modern building codes and make minor improvements to facilitate staff moving into City Hall from leased offices, Farrell said.

She said officials are also evaluating how to support physical distancing and other protective measures in the City Hall complex and other public facilities as the city resumes in-person services in the months ahead.

Two other projects are nearly complete.

Construction on the Civic Center Multipurpose Sports Field is coming to an end. The field was slated to open this summer and will open in accordance with public health guidance, Farrell said.

The $8.6 million field replaces 3.8 acres of the Civic Center parking lot and will provide space for residents of all ages to play soccer, rugby and lacrosse. City Council voted to turn the parking lot into a field in June 2018 after more than a decade of lobbying by local families, who argued that Santa Monica High School lacked space for outdoor sports.

Fire Station 1, a $41.2 million facility at 1337 7th St. in downtown Santa Monica, is almost finished. The 28,000-square-foot fire station replaces a seismically unsafe building constructed in the 1950s and will contain dormitories, offices, a community room, and space to house fire engines and equipment.

Construction is underway on City Yards and the Sustainable Water Improvement Project, or SWIP.

Farrell said the city is completing a facilities building under construction at City Yards and suspending all other construction on the $115 million renovation to City Yards in light of the budget gap.

The first phase of City Yards was slated to be completed in 2023, with an additional two phases of construction that would conclude by 2030.

SWIP, a $92.5 million water recycling system that will meet 12% of the city’s water demand when it is completed in 2022, will continue as planned, Farrell said. The project is funded through the city’s water and wastewater funds, which have not suffered a significant drop in revenues.

The system is projected to save the city money in the long term because it will allow the city to stop importing water by 2023. The water the city buys from the Metropolitan Water District of Southern California is more expensive per unit than water produced locally.

madeleine@smdp.com

Tags: capital projectsCity Hallconstance farrellcoronavirusprojects

Madeleine Pauker

Recent News

Ruskin, Jazz Bakery need help

Ruskin, Jazz Bakery need help

May 15, 2025
Around Town: Japanese Street Food Fest & More!

Around Town: Japanese Street Food Fest & More!

May 15, 2025
Street League Skateboarding’s biggest stars set to ‘takeover’ Santa Monica Pier

Street League Skateboarding’s biggest stars set to ‘takeover’ Santa Monica Pier

May 15, 2025
California approves State Farm's request for 17% premium increase for homeowners

California approves State Farm’s request for 17% premium increase for homeowners

May 14, 2025
Democrats seeking California governor strut their stuff for powerful union leaders

Democrats seeking California governor strut their stuff for powerful union leaders

May 14, 2025
Council adopts "soft launch" for Promenade entertainment zone with reduced hours of 6 p.m. - 2 a.m.

Council adopts “soft launch” for Promenade entertainment zone with reduced hours of 6 p.m. – 2 a.m.

May 14, 2025
Turf debate heats up in Santa Monica as district, parents clash over artificial grass

Turf debate heats up in Santa Monica as district, parents clash over artificial grass

May 14, 2025
Gov. Newsom pushes for more camping bans but local rules already surpass state proposals

Gov. Newsom pushes for more camping bans but local rules already surpass state proposals

May 14, 2025
Santa Monica Daily Press

Copyright © 2025 SMDP. All Rights Reserved.

Navigate Site

  • About
  • Our People
  • Print Advertising
  • Digital Advertising
  • Legal Notices
  • Obituary
  • SMDP Finder
  • Privacy Policy
  • Back Issues

Follow Us

No Result
View All Result
  • News
  • Community
  • Business
  • Lifestyle
  • Opinion
  • Sports
  • Events
  • ‘Tis The Season
  • Advertise
    • Print Advertising
    • Digital Advertising
    • Legal Notices
    • Obituary
    • Marriage & Other Special Announcements
  • Back Issues
  • Contact Us
  • Support Us

Copyright © 2025 SMDP. All Rights Reserved.

Skip to content
Open toolbar Accessibility Tools

Accessibility Tools

  • Increase TextIncrease Text
  • Decrease TextDecrease Text
  • GrayscaleGrayscale
  • High ContrastHigh Contrast
  • Negative ContrastNegative Contrast
  • Light BackgroundLight Background
  • Links UnderlineLinks Underline
  • Readable FontReadable Font
  • Reset Reset