Current Projects:

  1. Parking Structure #5 Tenant Improvement Project
  2. Parking Structure Repair Project
  3. EPA Grant Funded Water Infrastructure Reliability Improvement Project
  4. LA Metro Public Art Project – “Tears of Santa Monica”
  5. Bike Network Linkages Project
  6. Annual Water Main Replacement Project
  7. Advanced Traffic Management System, Phase 5 Project

 

PARKING STRUCTURE #5 TENANT IMPROVEMENT PROJECT

For the week of December 24, construction will take place in Parking Structure #5 at 1440 4th street and anticipates affecting the sidewalk in front of the building with the sidewalk pedestrian tunnel, lasting until 1/11/19 During this time, there may be intermittent closures of a single lane of south-bound traffic between 8:00 am and 3:00 pm Monday thru Friday. Should you have any questions, please contact Tim Purcell, Project Manager (310) 458-2205 ext. 5027

PARKING STRUCTURE REPAIR PROJECT

No work planned for the week of December 17. Please contact Robert Zak, Project Manager at (310) 458-2283 with any questions/concerns regarding this project.

EPA GRANT FUNDED WATER INFRASTRUCTURE RELIABILITY IMPROVEMENT PROJECT  

For the week of December 24, the contractor will continue working on Grand St between 6th St and Lincoln Blvd reconnecting services.  Traffic will be closed to thru traffic on Grant Street and on Ashland Ave. Please use alternate routes whenever possible. Should you have any questions, please contact Carlos Rosales, Project Manager (310) 458-8721 ext. 2620

LA METRO PUBLIC ART PROJECT – “TEARS OF SANTA MONICA”

For the week of December 24, construction may take place at the westerly wall of the Expo light rail station at 4th and Colorado. The project will run from Summer until the early part of Fall. Intermittent easterly sidewalk and northbound 4th Street lane closures will take place. For any questions or further information, please contact Henry Servín, at (310) 458-8291 or Leticia Ivins at LA Metro at IvinsL@metro.net and at (213) 922-6000, x2721 with any questions/concerns regarding this project.

BIKE NETWORK LINKAGES PROJECT  

For the week of December 24, work is scheduled to be take place on Ocean Park. The project consists of applying new green paint to existing bicycle lanes. Please contact Jason Hoang, Project Manager at (310) 458-8721 with any questions/concerns regarding this project.

ANNUAL WATER MAIN REPLACEMENT PROJECT  

For the week of December 24, no work is scheduled to take place.  The contractor will begin installing new water main on Lincoln Ct between Olympic Blvd and Colorado Ave on January 2, 2019. Traffic will be closed to thru traffic. Please use alternate routes whenever possible. Should you have any questions, please contact Carlos Rosales, Project Manager (310) 458-8721 ext. 2620

ADVANCED TRAFFIC MANAGEMENT SYSTEM, PHASE 5 PROJECT   

For the week of December 24, construction begins on the Advanced Traffic Management System, Phase 5 Project.  This project will upgrade the traffic signal equipment at four locations and install fiber optic cables along Montana Ave and 26th St.  The project will provide transit priority along the corridor, allow for real-time remote monitoring and management of the traffic signals, provide public Wi-Fi along the corridor, and connect the San Vicente Reservoir and the Montana Avenue Branch Library to the City’s network.  We appreciate your patience during the project, to provide this safety improvement and public enhancements. Please contact Andrew Maximous, Project Manager at (310) 458-8291 with any questions/concerns regarding this project.

Leave a comment